①先完成工序A,B,C,再完成工序D,E,F,最后完成工序G;
②完成工序A后方可进行工序B,工序C可与工序A,B同时进行;
③完成工序D后方可进行工序E,工序F可与工序D,E同时进行;
④完成各道工序所需时间如下表所示:
工序 | A | B | C | D | E | F | G |
所需时间/天 | 11 | 15 | 28 | 17 | 16 | 31 | 25 |
(2)现因情况有变,需将工期缩短到80天,工序A,C,D每缩短1天需增加的投入分别为5万元,4万元,6万元,其余工序所需时间不可缩短,则所增加的投入最少是